Site access from a public road for heavy traffic.

Getting trucks to a biogas plant, a hall or a farm starts with a decision by the road authority and ends with choosing a pavement for the traffic. Step by step, with the legal basis.

Chain of reasoning

Public road
  1. 01Assumption

    The road authority specifies the access location and technical parameters in the permit; it may refuse the permit or limit its duration on grounds arising from technical building regulations or principles of technical knowledge.

    Why

    The road authority's permit for the access location is needed whatever the road category.

    Public Roads Act, Building Law

    Read the section
  2. 02Dependency

    Where a building permit application or construction notification is required, the access-location permit is attached. The access-location permit expires if the access is not built within 3 years of issue.

    Why

    The road authority's permit is required even where construction of the access needs neither a building permit nor a notification, as is generally the case for municipal and district roads. Its expiry limits the time available to build the access.

    Public Roads Act, Building Law, art. 29(2)(11)

    Read the section
  3. 03Next step

    How many heavy vehicles, and of what kind, will come to the site?

    Why

    Traffic sets the KR traffic category and the choice of pavement structure under the GDDKiA catalogue.

    GDDKiA catalogue

    Read the section
01

Consent for the location of a site access junction

The location of a junction from a public road is approved by the road authority in a consent that sets out the place and the technical parameters of the junction. The authority may refuse, or issue the consent for a fixed period.

The consent expires if the junction is not built within 3 years of its issue. Building a junction on the basis of the consent does not require a zoning decision (WZ).

Basis: Journal of Laws 2025 item 889

02

Design and works in the road reserve

The consent contains a notice of the obligation to obtain the road authority's permit for works in the road reserve before they begin, and of the need to agree with the authority the site plan and the architectural design of the junction, where these are required.

The consent for the location of the junction is attached to the building permit application or to the notification.

Basis: Journal of Laws 2025 item 889

03

Notification of a junction onto a national or voivodeship road

As a rule, building junctions onto national and voivodeship roads does not require a building permit, but does require notification; a permit may be required in the cases set out in the Building Law. The notification goes to the voivode, the first-instance authority for works on national and voivodeship roads, who has 21 days to object.

Basis: Journal of Laws 2026 item 524

04

When a ZRID applies

The decision granting a road investment permit (ZRID) is issued by the voivode for national and voivodeship roads, or by the district head (starosta) for district and municipal roads, at the request of the relevant road authority, within 90 days.

A private investor therefore does not apply for a ZRID for their own junction. A ZRID arises when the road authority itself carries out an investment in a public road.

Basis: Journal of Laws 2024 item 311

05

Pavement matched to the traffic

The GDDKiA catalogue of typical flexible and semi-rigid pavement structures (annex to order no. 31 of 16 June 2014) classifies traffic from KR1 to KR7 by the total number of equivalent 100 kN axles per design lane over the design period: from 0.03 to 0.09 million for KR1 to more than 52 million for KR7.

The design period is 30 years for motorways and expressways and 20 years for other roads. That is why, before the junction design is prepared, we calculate how many vehicles, and of what kind, will come to the site.

Basis: GDDKiA catalogue 2014